The Marshall County Highway Department will begin the summer season chip and seal program on Monday, July 24th weather permitting. There are 14 different roads on the project list and it is estimated to sake several weeks to complete.
- 5B from Beech to County Line
- Beech from 6th Road to 3B
- Filbert from 6th to 7th
- Hawthorn from 5C to Plymouth Goshen
- 6B from Ironwood to King
- Juniper from 6th Road to Plymouth Goshen
- Union from 1C to County Line
- Pioneer from City Limits to State Road 17
- Overmyer Drive from State Road 17 to City Limits
- Olive Trail from Overmyer Drive to 14B
- Monterey Road from State Road 110 to County Line
- Fir Road from State Road 110 to 17th Road
- Lincolnway from City Limits to King Road
- Plymouth Goshen from City Limits to US 30
Each individual road will be closed during the chip and seal application but will reopen as soon as possible after.
The public is encouraged to drive with caution on the newly chip and sealed roads and avoid the closed areas during the process.